Skip to main content
Back to Resources
Case Study

ROI Case Study: 5-Axis CNC Investment

How a mid-sized shop achieved 18-month payback on a $250K investment

Company Profile

Background

  • Industry: Aerospace component manufacturing
  • Shop Size: 25 employees, 8,000 sq ft
  • Annual Revenue: $4.2M (pre-investment)
  • Existing Equipment: Three 3-axis VMCs, one 4-axis horizontal
  • Customer Base: Tier 2 aerospace suppliers, medical devices

Business Challenge

The shop was losing bids on complex parts requiring 5+ setups on 3-axis machines. Competitors with 5-axis capability were winning these jobs at 20-30% lower prices due to reduced labor and setup time.

Management identified $800K/year in lost opportunities from RFQs they couldn't competitively quote.

Investment Breakdown

Equipment Purchased

DMG MORI DMU 50 (5-Axis Universal)

  • • Travel: 500×450×400mm (X-Y-Z)
  • • Spindle: 18,000 RPM, 54 Nm torque
  • • Rotary axes: ±120° (A-axis), 360° (C-axis)
  • • Tool changer: 42 positions
  • • Heidenhain TNC 640 control
  • • Coolant through spindle

Total Investment

Machine base price$220,000
Installation & rigging$8,500
Tooling package (holders, fixtures)$15,000
CAM software upgrade (Mastercam 5-axis)$12,000
Operator training (2 weeks)$6,000
Programmer training (1 week)$4,500
TOTAL INVESTMENT$266,000

Financing: 60-month lease at 4.5% APR = $4,950/month

Financial Performance Analysis

Year 1 Results

$385K

New Revenue
(5-axis only jobs)

$92K

Cost Savings
(existing parts optimized)

$477K

Total Financial Benefit
(Year 1)

Revenue Sources Breakdown

Revenue CategoryYear 1Year 2Description
New aerospace contracts$285,000$420,000Complex brackets, turbine components
Medical implant work$68,000$125,000Titanium spinal implants (single-setup critical)
Mold/die contracts$32,000$85,000Complex cavity molds with undercuts
New Revenue Total$385,000$630,000Jobs not possible with 3-axis only

Cost Savings from Existing Parts

Part FamilyBefore (3-axis)After (5-axis)Annual Savings
Manifold blocks4 setups, 180 min cycle1 setup, 85 min cycle$38,000
Angled mounting brackets3 setups, 95 min cycle1 setup, 52 min cycle$31,500
Precision housings5 setups, 240 min cycle1 setup, 135 min cycle$22,800
Cost Savings TotalReduced labor + setup time$92,300

Investment vs. First Year Benefits

Total Investment: $266,000

Machine$220K
82.7%
Installation$8K
3%
Training$10K
3.8%
CAM Software$15K
5.6%
Tooling$13K
4.9%

Total Benefits: $477,300

New Revenue$385K
80.6%
Cost Savings$92.3K
19.4%
Net Benefit (Year 1)
$477K - $135K
= $342K Profit
Operating costs: $135K

ROI Calculation

Year 1 Financial Summary

New Revenue$385,000
Cost Savings (existing parts)$92,300
Total Benefit$477,300
Operating Costs:
Lease payments (12 months)$59,400
Tooling consumables$18,500
Additional labor (operator + programmer)$45,000
Energy, maintenance, insurance$12,000
Total Operating Costs$134,900
Net Profit (Year 1)$342,400
Payback Period
18
months

Target was 24-36 months

Year 1 ROI
129%
return

$342K profit on $266K investment

5-Year NPV
$1.8M
profit

Assuming 20% revenue growth/year

Key Success Factors

What Worked Well

  • Pre-sold $180K in contracts

    Before machine arrived, secured commitments from 3 customers

  • Invested in training upfront

    2 operators + 1 programmer trained before first job

  • Optimized existing parts first

    Re-programmed high-volume parts for 5-axis to prove capability

  • Targeted specific markets

    Focused on aerospace where 5-axis is required, not "nice to have"

Challenges Overcome

  • Steep learning curve (3 months)

    First jobs ran at 60% efficiency; solved with CAM templates

  • Collision risk on complex parts

    Implemented simulation software (Vericut) to prevent crashes

  • Workholding limitations

    Invested additional $8K in modular vises and tombstones

  • Programming time underestimated

    5-axis programs take 3-4x longer initially; improved with experience

Lessons Learned & Recommendations

Management's Advice for Others

1. Validate demand before buying

"We analyzed 18 months of lost quotes and confirmed $800K opportunity. Don't guess—use data."

2. Budget 15-20% extra for ecosystem costs

"The machine is just the start. CAM, simulation, workholding, tooling—it adds up fast."

3. Don't skimp on training

"Best $10K we spent. Operators confident from day one = faster ramp-up and fewer scrapped parts."

4. Start with familiar parts

"We re-programmed existing manifold blocks first. Knew the part, so could focus on 5-axis technique."

5. Market the capability aggressively

"Updated website, called every customer, went to trade shows. New capability = active sales effort."

Would They Do It Again?

"Absolutely. The 5-axis transformed our business. We went from competing on price for commodity work to winning high-margin contracts our competitors can't touch. Two years later, we bought a second 5-axis machine. It's not just ROI—it's survival in aerospace manufacturing."

— Operations Manager, Anonymous Aerospace Shop

18-Month Payback Timeline

Month 1-2

Installation, training, first test parts. Revenue: $12K (training parts only)

Month 3-6

Ramp-up phase. First production jobs. Avg revenue: $18K/month

Month 7-12

Full production. New customers onboarded. Avg revenue: $35K/month

Month 13-18

High-margin aerospace work. Avg revenue: $42K/month. Payback achieved!

Cumulative Cash Flow (18 Months)

$100K$50K$0-$50K-$100K-$150K-$200K-$266K
M0
-$266K
M3
-$210K
M6
-$138K
M9
-$55K
M12
+$28K
M15
+$110K
Payback! ✓
M18
+$190K
Negative Cash Flow
Positive Cash Flow (Payback)

Calculate Your Own ROI

Use our calculators to model the financial impact of adding 5-axis capability to your shop: