Technical Guide

ProNest Nesting Efficiency Best Practices

Achieve <5% material waste through optimized nesting

Why Nesting Efficiency Matters

For laser cutting operations, material waste typically ranges from 10-20% with basic nesting. Advanced ProNest techniques can reduce this to <5% waste, saving $50,000-$200,000 annually for medium-volume shops.

💰 Quick Math:

Shop using 1,000 sheets/month at $200/sheet:
15% waste = $30,000/month loss
5% waste = $10,000/month loss
Savings: $20,000/month = $240,000/year

Nesting Efficiency: Poor vs. Optimized

❌ Poor Nesting: 70% Efficiency

WASTE
Sheet: 2400×1200mm2.88 m²
Parts Nested:3 parts
Material Used:2.02 m²
Waste:0.86 m² (30%)
Cost @ $200/sheet:$60 wasted

✅ Optimized: 92% Efficiency

Sheet: 2400×1200mm2.88 m² (same)
Parts Nested:15 parts (+400%)
Material Used:2.65 m²
Waste:0.23 m² (8%)
Cost @ $200/sheet:$16 wasted ($44 saved)
Annual Material Savings (100 sheets/month)
22% efficiency gain × 1,200 sheets × $200 = $52,800 saved/year

Plus 20-30% faster cutting time from common line cutting

True Shape Nesting

Fit parts based on actual contours rather than rectangular bounding boxes.

ProNest Settings:

  • • Enable "True Shape" in Advanced tab
  • • Set rotation increment: 1° (finer = better fit)
  • • Allow part-to-part spacing: 3-5mm minimum
  • • Use "Best Fit" algorithm (slower but 5-8% better)

Impact: 5-10% material savings vs. rectangular nesting

Common Line Cutting

Share cutting paths between adjacent parts to eliminate duplicate cuts.

Setup Requirements:

  • • Parts must have identical edge profiles
  • • Enable "Common Line" in Nesting Options
  • • Set tolerance: 0.1mm (tighter = more opportunities)
  • • Works best with rectangular parts

Impact: 3-7% savings + 20-30% faster cutting time

Grain Direction Optimization

Orient parts to match material grain (for steel/aluminum) to prevent warping.

Best Practices:

  • • Set grain direction in Material Library (0° or 90°)
  • • Mark critical parts with "Grain Required" flag
  • • Allow 0° or 180° rotation only for grain-sensitive parts
  • • Use "Grain Aware" nesting mode

Trade-off: May reduce nesting efficiency by 2-3% but prevents $1000s in warped parts

Skeleton Reuse

Save leftover sheet remnants (skeletons) and nest small parts into them.

Implementation:

  • • Create "Remnant Library" folder in ProNest
  • • After nesting, save skeleton as .DXF if >30% usable area
  • • Label by size: "2400x1200-Remnant-45%"
  • • Nest small parts (<300mm) into remnants first

Impact: Additional 2-5% material recovery

Advanced Optimization Strategies

1. Multi-Sheet Planning

Nest across multiple sheets simultaneously to find global optimum instead of greedy per-sheet optimization.

ProNest Setup:

Step 1: Job Setup

  • • Import all parts for the week/day
  • • Group by material type and thickness
  • • Set sheet quantity: "Auto Calculate"

Step 2: Nest Settings

  • • Algorithm: "Best Fit" (not "First Fit")
  • • Run Time: 5-10 minutes per material
  • • Enable "Sheet Optimization"

Benefit: 3-6% better utilization vs. individual sheet nesting

2. Mixed Thickness Nesting (with Caution)

Nest different thicknesses on same sheet when total thickness variance is small (<2mm).

⚠️ Important Considerations:

  • • Only works if laser can auto-adjust focus (most modern systems can)
  • • Example: Mix 3mm + 4mm steel OK, 3mm + 6mm NOT recommended
  • • Requires careful NC program validation
  • • Best for low-volume custom work, avoid for production runs

3. Part Orientation Rules

Strategic part rotation can unlock significant nesting improvements.

Part TypeRotation StrategyReason
Circles, squaresAny angle (360°)Symmetrical - no difference
Rectangles0° or 90° onlyBest utilization with orthogonal alignment
Complex shapes1° incrementsFind optimal interlocking positions
Grain-sensitive0° or 180° onlyMaintain grain direction for strength

4. Edge Distance Optimization

Minimize edge distance while maintaining cut quality and part stability.

Sheet Edge:

5-10mm minimum

Too close = warping risk

Part-to-Part:

3-5mm typical

Material thickness dependent

Small Parts:

Use micro-joints

Prevent tip-up during cutting

Waste Reduction Targets by Operation

Operation TypeTypical WasteOptimized WasteKey Technique
Production runs (100+ parts)8-12%3-5%Multi-sheet + common line cutting
Mixed job shop (20-50 parts)12-18%5-8%True shape + skeleton reuse
Custom one-offs (<10 parts)15-25%8-12%Use remnants first, batch with future jobs
Large parts (>1000mm)10-15%5-7%Careful orientation, minimal edge distance
Small parts (<200mm)5-10%2-4%Fill remnants, tight spacing with micro-joints

30-Day ProNest Optimization Plan

Week 1

Baseline & Training

  • • Measure current waste %
  • • Train team on true shape nesting
  • • Review ProNest advanced settings
Week 2

Enable Core Features

  • • Activate common line cutting
  • • Set up grain direction rules
  • • Optimize rotation increments
Week 3

Remnant System

  • • Create remnant library
  • • Start saving skeletons >30%
  • • Nest small parts into remnants
Week 4

Multi-Sheet Planning

  • • Group jobs by material
  • • Run best-fit algorithm
  • • Measure waste improvement

Expected Result After 30 Days:

30-50% Waste Reduction

Example: 15% waste → 7.5-10.5% waste

Common ProNest Mistakes to Avoid

Using "First Fit" algorithm for production

First Fit is fast but wastes 5-8% more material. Use "Best Fit" for production runs.

Not saving skeletons

Remnants with >30% usable area are valuable. Label and save them for small parts.

Excessive edge distance

Default 15-20mm edge distance wastes material. Use 5-8mm for most materials.

Nesting one job at a time

Batch multiple jobs together for better overall utilization.

Ignoring grain direction

For structural parts, wrong grain orientation causes warping and failures.

Quick ROI Calculation

Example Shop Scenario:

Current State:

  • • Material usage: 1,000 sheets/month
  • • Cost per sheet: $200 average
  • • Current waste: 15%
  • Monthly waste cost: $30,000

After Optimization:

  • • Material usage: 1,000 sheets/month
  • • Cost per sheet: $200 average
  • • Optimized waste: 5%
  • Monthly waste cost: $10,000

Monthly Savings: $20,000

Annual Savings: $240,000

Investment in ProNest optimization training: ~$5,000
Payback period: <1 month